CONSTRUCTION WASTE MANAGEMENT IN MALLORCA

The following documentation related to the contruction-demolition waste (CDW) management is needed to apply for a municipal building permit at the town hall:

MAJOR CONSTRUCTION WORK:

1- Waste form (CDW deposit payment document).

2- Proof of deposit payment (Document of payment or bank guarantee).

3- The contract for processing with MAC Insular.

MINOR CONSTRUCTION WORK:

No documentation related to the Construction and Demolition Waste Management must be submitted, but it is obligatory to treat this waste properly (see point 4).

1. HOW TO FILL IN THE WASTE FORM OR PAYMENT DOCUMENT

In the event of major construction work, the construction manager or the person responsible for the project must fill in the payment document or form according to the work or project characteristics, thus obtaining the the amount to be deposited at the Consell de Mallorca. The form must be attached to the work execution project, it must be signed by the technician responsible and endorsed by the corresponding professional association.

The procedure can be checked on the Consell de Mallorca website, section “Gestión tributaria y recaudación” (Tax management and collection), “Fianza ordinaria” (Ordinary deposit) or “Fianza única de residuos de construcción-demolición para obras mayores” (Single deposit for construction-demolition waste from major construction works), as the case may be:

https://seu.conselldemallorca.net/

Follow the steps specified in the site to carry out the procedure.

2. HOW TO SUBMIT the DEPOSIT at the CONSELL DE MALLORCA

In the event of major construction work, the person responsible for generating the contruction-demolition waste must pay the deposit indicated in the waste form or payment document.

The procedure can be checked on the Consell de Mallorca website, section “Gestión tributaria y recaudación” (Tax management and collection), “Fianza ordinaria” (Ordinary deposit) or “Fianza única de residuos de construcción-demolición para obras mayores” (Single deposit for construction-demolition waste from major construction works), as the case may be:

https://seu.conselldemallorca.net/

Follow the steps specified in the site to carry out the procedure

3. HOW TO SIGN A CONTRACT FOR PROCESSING WITH MAC INSULAR

In the event of major construction work, the contract for processing with MAC Insular must be completed and signed in order to properly manage the construction-demolition waste. The procedure is available at www.mac-insular.com, section “Gestiones usuarios” (User management).
The contract must be submitted at the town hall when applying for the building permit. As soon as you receive the license number, you must communicate it to MAC Insular in order to include it in the contract.



To set up direct debit the following documentation must be submitted with the agreement:

    INDIVIDUAL:
  • DNI
  • Bank certificate featuring the IBAN code
    COMPANY:
  • Copy of the representative’s ID.
  • Bank certificate featuring the IBAN code.
  • Any additional documentation may be requested.

If the customer has decided to set up a direct debit, a monthly invoice with the tones delivered will be issued; otherwise, an invoice at the time of unloading will be issued at the plant which must be paid at the time of delivery. The payment can be made in cash or by credit card

4. SEPARATE WASTE AT SOURCE

Preferably on the construction site, waste must be separated, according to art. 30 of Law 7/2022 on waste, into:



Hazardous:
contaminated cans, tubes... (with paint or varnish remnants), any material containing asbestos...



    Non-hazardous: which must be separated, at least, into:
  • Minerals: Concrete, briks, tiles, ceramics and stone.
  • Metals.
  • Woods.
  • Plastics.
  • Glass.
  • Gypsum.
  • Other waste.

Hazardous waste: must be delivered to duly authorised waste managers.
These managers can be consulted in the Waste Production and Management Register, at http://residus.caib.es.

Non-hazardous waste: generated must be delivered to one of the eight plants of MAC Insular (concessionary of the compulsory Island Public Service), which are located all over the island.

CUSTOMER’S OFFICE:
From Monday to Thursday: from 07:30 to 17.00.
(From 15/06 to 15/09: from 07:30 to 15:30).
Friday: from 07.30 to 15:00.


WASTE RECEPTION:
PT1-Bunyola and CTP5-Calvià:
From Monday to Friday:
From 07:30 to 18:30.
Saturday: From 08:00 to 12:00.
PT2-Santa Margalida, CTP1-Inca,
CTP2-Llucmajor, CTP3-Artà,
CTP4-Manacor, CTP6-Porreres:

From Monday to Friday:
From 08:00 to 16:00.
Saturdays closed.


Waste transport must be done through a registered waste transportation company and must be accompanied by the Identification Document regulated in art. 51 of Law 8/2019 on waste and contaminated soils of the Balearic Islands, in RD 553/2020 on waste shipment and in art. 31 of Law 7/2022 on waste.

When the customer’s waste delivery is done by a third-party, an authorization document from the customer to the transporter (available at www.mac-insular.com, “Downloads”) must be submitted at the time of delivery at the plant, for each load delivered to MAC Insular. This authorization must be signed by the customer and the transporter, and contain both the personal details of the customer and the transporter, and the construction details (license number, location, type of construction and load details).

5. HOW TO APPLY for the DEPOSIT REIMBURSEMENT at the CONSELL DE MALLORCA

For major construction work, after the construction has been completed and once the end of work certification has been issued either by the town hall or by the responsible construction technician, the customer must then apply for:

5.1. A MAC Insular certificate to confirm the correct management of the construction-demolition waste, necessary to request the return of the deposit at the Consell de Mallorca. The procedure is available at www.mac-insular.com, section “Gestiones usuarios” (User management).

5.2. The return of the deposit at the Consell de Mallorca. The procedure is available on the Consell de Mallorca website, section “Gestión tributaria y recaudación” (Tax management and collection), “Fianza ordinaria” (Ordinary deposit) or “Fianza única de residuos de construcción-demolición para obras mayores” (Single deposit for construction-demolition waste from major construction works), as the case may be:

https://seu.conselldemallorca.net/

Follow the steps specified on the website to carry out the procedure.